Project Background

A brand new sewage pumping station, the first building to be completed on the Olympic Site. At the heart of the station are two 4 metre tall filters, decorated in the Olympic ‘pink’ colour (and affectionately nicknamed Pinky and Perky) which prevent odours escaping from the sewage plant. The stylised sewage plant has even been awarded a prestigious London Architectural Award for its striking design.

Application

Silicone 825 was used to seal pre cast joints internally and externally with the joint dimensions below and Silicone 450 was used to seal the external joints on the tower at the top.

This was due to colour match.

Pudding Mill Lane Sewage Pumping Station Pudding Mill Lane Sewage Pumping Station Pudding Mill Lane Sewage Pumping Station Pudding Mill Lane Sewage Pumping Station Pudding Mill Lane Sewage Pumping Station

Click images to enlarge

Project Start Date

June 2009

Project Completion Date

September 2009